Building 68 Rehabilitation Project

The intent of the project is to rehabilitate an existing building that was formerly used for dewatering and make it more suitable for dry storage and forklift access. The scope of the project will include, leveling the existing concrete floor by saw cutting, grinding and placing a topping slab; replacing roofing materials, repairing spalled concrete, recoating structural elements and closing existing penetrations and openings in the masonry walls.

Status

Bidding Closed

Prebid Date 7/11/23 10:00am
Bid Date 7/27/23 2:00pm

Company & Contacts

Vallejo Waste Water District
Bill Ash  
707-651-7139

Location

Vallejo, CA

Documents

Construction Cost Estimate: $275,000